Newgeophysicalinterpretation confirmslarge magnetictargetsatour
Patmungala and Dumunziareasin the WestArunta
Highlights
• A 3.5km wide, piped-shaped magnetic anomalyconfirmed atPatmungula.
• LMShasinitiatedakeyinvestmentinagravitysurveyprogrammetofurtherassess
this large anomaly to assistdrillhole targeting.
• Northern Territory Geological Survey is supporting the deep drilling program of
this target.
• Additional gravity survey to be completed over the Dumunzi magnetic target,
north ofSilverKing, at the intersectionofseveralprominentstructures.
• Soil sampling of selected targets will compliment data acquisition for these
gravitysurveys.
LitchfieldMineralsLimited(“Litchfield”orthe“Company”)(ASX:LMS),acompanywith
a strategic emphasis on critical minerals, is pleased to announce the start of a ground
gravity campaign at the Mt Doreen project by Planetary Geophysics. The main focus of
the gravity survey is the Patmungala magnetic anomaly, that we have named megalith
which could potentially represent an IOCG or deeply buried igneous intrusive complex
(Figure 1). An additional survey will be completed at the Dumunzi target, located north
ofthe SilverKingprospect.
Patmungula megalith target
The megalith anomaly is a significant magnetic target identified through inversion
modelling of Annie Springs Rio Tinto Aeromanetic survey from 19971
revealing a deep,
3.5kmwide,sub-verticalanomalyofunknownorigininthePatmungalaareaofourMount
Doreen tenement package (EL31305) in the West Arunta. As announced on 11 June
20242
,theNorthernTerritoryGeologicalSurvey(NTGS)hassupportedthemegalithtarget
with funding of up to $140,000 for drilling a deeper hole. We plan to complete this deep
drilling once we receive all the data from the gravity, structural, and VTEM surveys in the
coming months.
1
Detailsof the Rio Tinto Magnetic Survey can be found at 1998. Annie Spring EL 9413. Second Annual
Report for the Period ending15th May 1998. Northern Territory Geological Survey, Open File Company
Report CR19980436.
2
Refer ASX Announcement – Drilling GrantsReceived from Northern Territory Government – 11/06/2024
2 | P a g e
Figure 1 – Total Magnetic Intensity (TMI) image of a 3.5km wide piped shape magnetic
targetin thePatmungalaarea.
The magnetic target appears to have structures that extend southeast into known zones
of base metal mineralisation within the Patmungala mineralisation zone. Historical
exploration(RoebuckResources3
)identifiedcopperandgalena-bearingquartzveinswith
copper rock chips to 6.2% Cu and low-level Ag and Au (Figure 2). The area also contains
numerous ferruginous, carbonate-rich horizons hosted within the volcano-sedimentary
PatmungalaBeds.
Ground gravity is currently underway by Planetary Geophysics to better delineate the
structure and help refine drillhole targeting. We will provide more information on this
target as we gatheradditionaldata inthe comingweeks.
3
Detailsof the Roebuck Resourcesgeological and geochemical mapping have been supplied in the
Litchfield MineralsIndependent Geologist Report, January 24th, 2024. Refer to the Litchfield Minerals
website for this report.
3 | P a g e
Figure 2– Quartz-malachite mineralization at thePatmungalacopper prospect.
Dumunzi target
Our recent aeromagnetic campaign has identified a significant magnetic target located
north of the Silver King prospect (Figure 3). This target, named Dumunzi, is situated in a
potential dilational zone at the intersection of several prominent geological structures4
as mapped by the NTGS, 250k Mount Doreen geological interpretation. The target is
completely covered by shallowalluvialsediments, less than 10 mdeep.
Over the next few days, a gravity survey will be conducted over parts of this anomaly. In
addition, the Litchfield team will be performing preliminary soil sampling in the area to
testforbase metaland rare earth elementfertility.
4
Detailsof the structure at Dumunzi can be found at the 1995, Mount Doreen, 250kGeological Map
GIS Data. Northern TerritoryGeologicsal Survey, Open File Sheet SF5212
4 | P a g e
Figure 3– Dumunzi target representedby RTP 1VD SUN HEQ,northof SilverKing.
CautionaryNote –Visual Estimates ofMineralisation
Any references to visual results above, made in the Patmungula section, are based on
observations from historical explorers. These visual observations, which identify
mineralisation, are derived from historical reports. Accurate and representative
estimates ofcopper andother metal contentrequire laboratory assays.
About Litchfield Minerals
Litchfield Minerals is a critical mineral explorer, primarily searching for base metals and
uranium out of the Northern Territory of Australia. Our mission is to be a pioneering
copper exploration company committed to delivering cost-effective, innovative, and
sustainable exploration solutions.
We aim to unlock the full potential of copper and other mineral resources while
minimising environmental impact, ensuring the longevity and affordability of this
essentialmetal forfuture generations.
5 | P a g e
We are dedicated to involving cutting-edge technology, responsible practices, and
stakeholder collaboration drives us to continuously redefine the industry standards and
delivervalue toourinvestors, communities, andthe world.”
The announcementhas beenapproved bythe BoardofDirectors.
Forfurtherinformation please contact:
Matthew Pustahya
Matthew@litchfieldminerals.com.au
JaneMorgan
jm@janemorganmanagement.com.au
Followus on:
www.litchfieldminerals.com.au
https://twitter.com/Litchfield_LMS
https://www.linkedin.com/company/litchfield-minerals-limited/
Competent Person’s Statement
The information in this Presentation that relates to Exploration Results is based on, and
fairly represents, information and supporting documentation compiled by Mr Russell
Dow (MSc, BScHons Geology), a Competent Person who is a Member of the Australian
Institute of Mining and Metallurgy (AusIMM) and is a full-time employee of Litchfield
Minerals Limited. Mr Dow has sufficient experience that is relevant to the style of
mineralisation and types of deposits under consideration and to the activity being
undertaken to qualify as a Competent Person as defined in the 2012 Edition of the
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves” (JORC Code). Mr Dow consents to the inclusion in the report of the matters
based onhis informationin the formandcontextin whichit appears.
Forward-LookingStatements and Important Notice
Statements regarding plans with respect to Litchfield’s project are forward-looking
statements. There can be no assurance that the Company’s plans for the development
of its projects will proceed as currently expected. These forward-looking statements are
based on the Company’s expectations and beliefs concerning future events. Forward-
looking statements are necessarily subject to risks, uncertainties, and other factors,
manyofwhichareoutsidethecontroloftheCompany,whichcouldcauseactualresults
todiffermaterially from suchstatements.
6 | P a g e
JORCCode,2012
Edition–Table1 Report
MtDoreenAeromagneticSurvey
Section1SamplingTechniquesandData
(Criteriainthis section apply toall succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases more explanation may be required,
such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
• No drilling reported in this release.
• LMS is reporting a new airborne survey at the Mt Doreen project.
• The airborne magnetic and radiometric survey was conducted by
MagSpec Airborne Surveys. MagSpec acquired the data with a
fixed-wing aircraft (Cessna 210).
• 100m survey line spacing and 30m flying height above ground
level (Mt Doreen North), 50m line spacing and 30m flying height
for Mt Irene and Silver King.
• Sample spacing 3.5m for magnetics and 35m radiometrics.
• Magnetometers: G-823A cesium vapour magnetometer.
• Gamma Ray Spectrometer: RSI RS-500 gamma-ray
spectrometer with 1024 Channels, incorporating 2x RSX-4
detector packs (32L).
• GPS: Integrated Novatel OEM719 DGPS receiver, 555 Channel
with L1/L2 + GLONASS Multi Frequency.
• Altimeter: Bendix/King KRA 405 radar altimeter and Renishaw
ILM-500R laser altimeter.
• Data Acquisition System: Integrated Novatel OEM DGPS
receiver, High precision cesium vapour magnetometer (sample
rates 20Hz).
7 | P a g e
Criteria JORC Code explanation Commentary
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
• No drilling was conducted.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
• Not applicable as no sampling conducted or reported.
Logging • Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• Not applicable for aeromagnetic survey.
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core
taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
• Not applicable for aeromagnetic survey.
8 | P a g e
Criteria JORC Code explanation Commentary
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is considered
partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (ie lack of bias) and precision have been established.
• The survey quality control (QC) parameters and tolerances are
listed in below table:
• A dedicated PC-based notebook computer was used as a
workstation to process and image geophysical and navigation
data acquired during the survey, producing semi-final,
preliminary levelled grids and maps.
• Flight path plots were generated from the GPS data to verify the
completeness and accuracy of each day's flight(s).
• The Geosoft software system permitted preliminary maps to be
9 | P a g e
Criteria JORC Code explanation Commentary
quickly and efficiently created for errors and coherency checks.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Flight data quality and completeness were assured by both
statistical and graphical means on a daily basis (Digital Data
Verification).
• Sampling and assay verification not applicable for aeromagnetic
survey.
Location of
data points
• Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• The coordinates were confirmed as being WGS84 UTM zone
52S.
• On-board DGPS positioning of all data locations.
• Traverse lines were surveyed at an average spacing of 100m.
• Control tie lines on block were surveyed at an average spacing
of 1000m.
• The survey was planned at 30m above ground at one
dimensional tight drape. The target accuracy for the aircraft
was± 10m from the planned elevation.
Data spacing
and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and
classifications applied.
• Whether sample compositing has been applied.
• The pre-processed data sampling rates for the sub-systems are:
o Magnetic data (20Hz)
o Radiometric data (2Hz)
o Airborne GPS (20Hz)
o Base station magnetometer (0.5Hz).
Orientation of
data in
relation to
geological
structure
• Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
• If the relationship between the drilling orientation and the orientation
of key mineralised structures is considered to have introduced a
sampling bias, this should be assessed and reported if material.
• Magnetic survey lines were flown 090-270 degrees (E-W).
• Drilling orientation not applicable for aeromagnetic survey.
Sample
security
• The measures taken to ensure sample security. • A report of daily activity covering the total acquisition period
prepared. The report covers production figures, flight duration
10 | P a g e
Criteria JORC Code explanation Commentary
times and daily comments on data QA/QC.
• All data collected under strict security measures by contractor.
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data. • All digital airborne magnetic and radiometric data was subject to
auditing by independent geophysical contractor, Xcalibur
Airborne Geophysics.
• No other audits or reviews were reported.
Section2ReportingofExplorationResults
(Criterialisted intheprecedingsection alsoapply to thissection.)
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint
ventures, partnerships, overriding royalties, native title interests,
historical sites, wilderness or national park and environmental
settings.
• The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
• The mineral tenement is held by Litchfield Minerals Limited
(ASX: LMS).
• The area has a granted Exploration License (EL31305) granted
by the NTGS on 6/6/2018, expires 5/6/2026.
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by other parties. • Refer to Section 6 and 7 in the Independent Geologists Report
(IGR) by Ross et al., 2023 for further detail. A summary of
previous exploration and mining is presented below.
• 1930- 1956: Minor amounts of copper and tungsten extracted
from Silver King, Clark, Mount Irene and Wolfram Hill.
• 1969: NT Mines & Water Resources diamond drilling at Clark
workings.
• 1987 – 2006: White Industries/Mareeba Mining, Bruce and Mules,
MIM Exploration/Roebuck Resources, Track Minerals, Poseidon
Gold/Yuendumu Mining, BHP, Homestake Gold, Rio Tinto
11 | P a g e
Criteria JORC Code explanation Commentary
• Rio Tinto Exploration, 1998. Annie Spring EL 9413. Second
Annual Report for the Period ending 15th May 1998. Northern
Territory Geological Survey, Open File Company Report
CR19980436.
•
• Exploration and Tanami Gold completed geological mapping,
geochemical sampling, airborne and ground geophysical surveys,
and drilling programs.
•
Geology • Deposit type, geological setting and style of mineralisation. • Refer to Section 5 in the Independent Geologists Report (IGR)
by Ross et al., 2023 for further detail. In summary:
• Mount Doreen is located in the southern portion of the
Paleoproterozoic Aileron Province of the Arunta Region.
• The oldest rocks at Mount Doreen are the multiply deformed and
metamorphosed siliciclastic sediments of the Lander Rock
Formation. The younger volcano sedimentary Patmungala Beds
lie in the south of the tenement, and both are intruded by the
Yarunganyi Granite. Numerous major faults strike close to east-
west and often contain veins or vein swarms of quartz, forming
ridges. Neoproterozoic to Palaeozoic sedimentary rocks of the
Ngalia Basin overlie the Aileron basement in the southwest of the
tenement and along the southern boundary.
• Mineralisation is considered to be epigenetic intrusion-related
breccia and vein mineralisation with polymetallic copper-lead-
zinc-silver-molybdenite and tungsten. Mineralisation is
interpreted to be from varied sources and associations as
evidenced from mineralisation dating.
12 | P a g e
Criteria JORC Code explanation Commentary
• The most prominent mineralisation is supergene copper at Silver
King with varying lead-zinc-silver- in quartz veins and shear
zones.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of the report, the Competent Person should clearly
explain why this is the case.
• Not applicable as no drilling is reported.
Data
aggregation
methods
• In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually Material and should be stated.
• Where aggregate intercepts incorporate short lengths of high grade
results and longer lengths of low grade results, the procedure used for
such aggregation should be stated and some typical examples of
such aggregations should be shown in detail.
• The assumptions used for any reporting of metal equivalent values
should be clearly stated.
• Not applicable, as no drill assay or similar interval results are
reported.
Relationship
between
• These relationships are particularly important in the reporting of
Exploration Results.
• Not applicable as no drilling or sampling reported.
13 | P a g e
Criteria JORC Code explanation Commentary
mineralisation
widths and
intercept
lengths
• If the geometry of the mineralisation with respect to the drill hole angle
is known, its nature should be reported.
• If it is not known and only the down hole lengths are reported, there
should be a clear statement to this effect (eg ‘down hole length, true
width not known’).
• This release has no reference to previously unreported drill
results, sampling, assay, etc.
Diagrams • Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include, but not be limited to a plan view of drill
hole collar locations and appropriate sectional views.
• The diagram in the body of this release is derived from the
airborne geophysical survey undertaken by MagSpec Airborne
Surveys.
Balanced
reporting
• Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting of
Exploration Results.
• This report provides the total information available to date and is
considered to represent a balanced report.
Other
substantive
exploration
data
• Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical
survey results; geochemical survey results; bulk samples – size and
method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential
deleterious or contaminating substances.
• No additional data is reported.
Further work • The nature and scale of planned further work (eg tests for lateral
extensions or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling areas,
provided this information is not commercially sensitive.
• Data modelling and completion of lithostructural interpretation.
Identified targets to be tested with surface geochemical
techniques and drilling.
Share your feedback
Discover